IRS Provides Relief on Begin Construction Continuity Requirements

Yesterday, the Internal Revenue Service (IRS) issued Notice 2021-41 (the Notice), providing relief for continuity requirements for the investment tax credit (ITC) under Section 48 and the production tax credit (PTC) under Section 45.

The applicable tax rate for the ITC and PTC is based on the year a project “begins construction.” Under existing IRS guidance, projects are treated as having begun construction by either satisfying the Physical Work Test or the Five Percent Safe Harbor. Both methods require a taxpayer to make continuous progress toward completion of the facility once construction has begun (Continuity Requirement). The IRS previously provided a Continuity Safe Harbor, whereby the Continuity Requirement will be deemed met if the project is placed in service within a certain number of years from beginning construction. For most projects, the Continuity Safe Harbor was previously four years and was extended to five years last year for projects that otherwise began construction in 2016 or 2017. Under the existing guidance, if the Continuity Safe Harbor is not met, a taxpayer can satisfy the Continuity Requirement by meeting the Continuous Construction Test (in the case of the Physical Work Test) or the Continuous Efforts Test (in the case of the Five Percent Safe Harbor). The Continuous Construction Test and Continuous Efforts Test are both demonstrated through facts and circumstances.

In the Notice, the IRS further extended the Continuity Safe Harbor to six years for projects that otherwise began construction in 2016 through 2019 and to five years for projects that otherwise began construction in 2020. In other words, the Continuity Safe Harbor will be satisfied if a taxpayer places the project in service by the end of a calendar year that is no more than five or six years (as applicable) after the calendar year during which construction of the project otherwise began.

The Notice further provides that for a project that does not satisfy the Continuity Safe Harbor, the taxpayer can satisfy either the Continuous Efforts Test or Continuous Construction Test (regardless of whether the taxpayer is relying on the Physical Work Test or the Five Percent Safe Harbor). Under previous guidance, a taxpayer relying on the Physical Work Test was all but certain to fail the Continuous Construction Test, which seems to require regular physical work from the time construction begins. The Continuous Efforts Test appears to encompass more activities than the Continuous Construction Test and may be easier to satisfy for some taxpayers.

The Notice clarifies that the relief was in response to the fact that “regional, national, or global circumstances due to the COVID-19 pandemic have continued to cause delays in the development of certain facilities eligible for the PTC and the ITC. These extraordinary delays have adversely affected the ability of many taxpayers to place facilities in service in time to meet the Continuity Safe Harbor.”

The Notice will be welcome relief to many taxpayers who have struggled with project delays in recent years.




read more

IRS Revises Recent Begin Construction Guidance

On May 18, 2016, the Internal Revenue Service (IRS) revised Notice 2016-31 (Notice), its recent guidance on meeting the beginning of construction requirements for wind and other qualified facilities (including biomass, geothermal, landfill gas, trash, hydropower, and marine and hydrokinetic facilities). For a discussion of the Notice, click here. The revisions clarify that the Continuity Safe Harbor is satisfied if a taxpayer places a facility into service by the later of (1) the calendar year that is no more than four calendar years after the calendar year during which construction of the facility began, or (2) December 31, 2016. The revisions also include additional language that the Notice applies to any project for which a taxpayer claims the Section 45 production tax credit (PTC) or the Section 48 investment tax credit (ITC) that is placed in service after January 2, 2013.

The revised Notice also corrects mathematical errors in an example illustrating the application of the begin construction guidance in the Notice to retrofitted facilities. The revised example is as follows:

A taxpayer owns a wind farm composed of 13 turbines, pad and towers that no longer qualify for either the PTC or the ITC. Each facility has a fair market value of $1 million. The taxpayer replaces components worth $900,000 on 11 of the 13 facilities at a cost of $1.4 million for each facility. The fair market value of the remaining original components at each upgraded facility is $100,000. Thus, the total fair market value of each upgraded facility is $1.5 million. The total expenditures to retrofit the 11 facilities are $15.4 million. The taxpayer applies the single project rule. Because the fair market value of the remaining original components of each upgraded facility ($100,000) is not more than 20 percent of each facility’s total value of $1.5 million, each upgraded facility will be considered newly placed in service for purposes of the PTC and the ITC. Accordingly, if the taxpayer pays or incurs at least $770,000 (or 5 percent of $15.4 million) of qualified expenditures in 2016, the single project will be considered to have begun construction in 2016. Provided the taxpayer also meets the Continuous Efforts Test, each upgraded facility will be treated as a qualified facility for purposes of the PTC. However, no additional PTC or ITC will be allowed with respect to the two facilities that were not upgraded.

Taxpayers should consider talking with their advisors to discuss the application of these rules to their projects.




read more

IRS Issues Additional Guidance on Beginning of Construction Rules for Renewable Projects

The Internal Revenue Service issued Notice 2015-25 on March 11, 2015, to provide further guidance on meeting the beginning of construction requirements for wind and other qualified facilities. The Notice extends the date by which a facility can meet the beginning of construction deadline to correspond with the extension of Code Section 45 passed by Congress at the end of 2014.

Read the full article.